The Kazimier garden



This was a job that I coordinated for the Kazimier in 2014 , we only had two weeks to
finish the main structures.



The old stage had to be dismatled
All the wood was  reused to build the train platform opposite

the first two pillars
The rest of the pillars had to be temporarely supported
It was not enough wood so we had to bring a truck full of reclaimed beams in order to continue

















We decided it was a good idea to live some skylights on the train platform 
The train carriage was put together in a day!!!
It was The fourth time we did it though



Fresh gravel and everything was starting to look good !!!

Nearly there !!!



Some vintage items!!!

Burnt out furniture


Finished !!!

 